Sibanye Stillwater Smelter

Client Profile
Case Study
Even though funding for the solar project was earmarked in the first quarter of 2017, the project did not go out to bid until September and the contract finalized in late October. Based upon funding sources, there was a strict deadline of project completion before the end of the year. The OnSite Energy team worked efficiently through the design and engineering phase in order to finalize equipment procurement and schedule construction to start the first week of December. As with any solar installation in Montana in December, there are bound to be weather challenges, not to mention short days and icy roads. As always, we were very proud of the dedication of our installation crew to work through challenging conditions to make sure our clients needs were met. Another successful project and more solar energy on the grid!